Question # 17

Which of the following would a project manager do NEXT after selecting a vendor for a project?

A.

Determine a list of qualified sellers.

B.

Determine vendor resource availability.

C.

Hold a bidders conference.

D.

Negotiate the contract.

Full Access
Question # 18

Which of the following contract types places the LEAST amount of risk on the seller?

A.

Fixed-Price

B.

Cost-Plus-Fixed-Fee (CPFF)

C.

Cost-Plus-Fee (CPF)

D.

Time and material

Full Access
Question # 19

The project team is recognized for contribution efforts and is officially released from the project during which of the following stages?

A.

Formal acceptance

B.

Administrative closure

C.

Lessons learned

D.

Transition plan

Full Access
Question # 20

The communication plan for a project is a subset of which of the following documents?

A.

Project charter

B.

Risk management plan

C.

Project schedule

D.

Project plan

Full Access
Question # 21

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?

A.

Bottom-up estimating

B.

Rolling wave planning

C.

Resource leveling

D.

Fast tracking

Full Access
Question # 22

Which of the following would be the benefit of saving a project binder in a centralized location?

A.

Provides an opportunity for another project manager to review the binder and make corrections.

B.

Provides an opportunity for team members to review their contributions.

C.

Provides other project managers the opportunity to review the project information.

D.

Provides stakeholders the opportunity to modify the change request forms.

Full Access
Question # 23

When a project ends unexpectedly, which of the following should the project manager do?

A.

Create an end document to add to the file before moving on to another project.

B.

Create a document identifying the negative impact of the early project ending to give to the customers management.

C.

Perform project close out with full documentation and review.

D.

Perform a limited project close that consists of releasing team members.

Full Access
Question # 24

A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?

A.

The costs are currently over the estimates.

B.

The costs and the estimates are about the same.

C.

The costs are currently under the estimates.

D.

The earned value is greater than the actual cost.