Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

Note! Following JK0-017 Exam is Retired now. Please select the alternative replacement for your Exam Certification.

JK0-017 Exam Dumps - CompTIA E2C Project+ Certification Exam

Go to page:
Question # 25

Quality assurance is performed during which phase of a project?

A.

During the controlling phase

B.

During both controlling and execution phase

C.

During the execution phase

D.

During the planning phase

Full Access
Question # 26

Which of the following is the FINAL step in pre-project setup?

A.

Complete the work breakdown structure (WBS).

B.

Sign the approval document.

C.

Create the needed stakeholder forms.

D.

Validate the project.

Full Access
Question # 27

All of the following are taken into account when determining the critical path EXCEPT:

A.

Late start and finish dates.

B.

Activity durations.

C.

Early start and finish dates.

D.

Resource limitations.

Full Access
Question # 28

Changing the project schedule to prevent a known risk is an example of which of the following risk responses?

A.

Mitigation

B.

Avoidance

C.

Acceptance

D.

Transference

Full Access
Question # 29

A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?

A.

Minimizes risk due to decreased timeline.

B.

Requires planning and execution to be completed in parallel.

C.

Minimizes cost since work is completed in four months instead of six.

D.

Requires rework due to decreased timeline.

Full Access
Question # 30

It is important to complete a formal project closure process to: (Select Three).

A.

assure that the customer will work with all vendors in the future.

B.

confirm that the stated project objectives were met.

C.

confirm that the customer accepts the final deliverables.

D.

collect new information to enter into the issue log for further review.

E.

assure that the contract is complete and the team members can be released.

F.

collect additional scope requirements that need to be entered into the project plan.

Full Access
Question # 31

Which of the following describes a quality control tool used to analyze defects based upon number of occurrences?

A.

Pareto diagram

B.

Scatter diagram

C.

Fishbone diagram

D.

Ishikawa diagram

Full Access
Question # 32

A project manager receives formal leadership authority from which of the following documents?

A.

Resource matrix

B.

Project charter

C.

Work Breakdown Structure (WBS)

D.

Statement of Work (SOW)

Full Access
Go to page: