Question # 41

A project manager has been engaged to deliver a project in South America and does not speak Spanish. More than 50 percent of the project team will be Spanish speaking. Which of the following would be the project managers BEST option?

A.

Insist that all communication be in English.

B.

Use automated translation technologies to communicate with team members in writing.

C.

Engage only bi-lingual team members.

D.

Engage interpreters at both locations for all key team communication.

Full Access
Question # 42

Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

A.

Request for Proposal (RFP)

B.

Quality management plan

C.

Change control board

D.

Version control system

Full Access
Question # 43

During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?

A.

Ensure that project team members do not work in very windy weather.

B.

Ensure that project team members are furnished with slip-resistant boots.

C.

Ensure that project team members are trained in injury response.

D.

Ensure that project team members are covered by applicable insurance.

Full Access
Question # 44

Which of the following BEST describes the chart of accounts?

A.

The numbering system used to monitor the quality measurements during the life of the project.

B.

The numbering system used to track project costs depending on their activity type.

C.

The numbering system used to decompose project activities into sub-project activities.

D.

The numbering system used to identify each activity on the work breakdown structure.

Full Access
Question # 45

Which of the following is created as part of the closing phase?

A.

Quality baseline

B.

Cost review

C.

Activity estimation

D.

Feasibility analysis

Full Access
Question # 46

Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?

A.

Compromising

B.

Negotiation

C.

Estimating

D.

Padding

Full Access
Question # 47

The project manager needs to determine the relationship between two variables. Which of the following tools will the project manager use?

A.

Histogram

B.

Run chart

C.

Pareto chart

D.

Scatter diagram

Full Access
Question # 48

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?

A.

Update the project plan to accommodate the changes.

B.

Perform an impact analysis.

C.

Organize a stakeholder meeting to review the changes.

D.

Change the project scope to reflect the change request.

Full Access