The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?
An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:
Project team members are confused about their roles on a project. Which of the following is the FIRST technique the project manager can use to define their roles?
A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?