New Year Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PK0-004 Exam Dumps - CompTIA Project +

Go to page:
Question # 73

During a risk review session, the project team identified the percentage probability that a particular risk will

occur. This is known as:

A.

risk identification

B.

risk prioritization

C.

risk qualification

D.

risk quantification

Full Access
Question # 74

The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?

A.

Personal preferences and message content

B.

Level of message/report detail and confidentiality constraints

C.

Time zones and language barriers

D.

Technological and criticality factors

Full Access
Question # 75

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

A.

Ask the team member to move to a different test environment.

B.

Ask the team member to refrain from testing the scenarios.

C.

Revisit the risk management plan and provide corrective actions.

D.

Revisit the contingency plan and provide corrective actions.

Full Access
Question # 76

Which of the following are the roles involved in a Scrum project?

A.

Scrum master, development team, quality coach

B.

Scrum master, business analyst, product owner

C.

Scrum master, product owner, development team

D.

Scrum master, project sponsor, business analyst

Full Access
Question # 77

A project manager is analyzing the cost variances produced when comparing two different projects completions.

Which of the following factors could be causing the increased variance for the four-month projects? (Select two.)

A.

Increased resource productivity

B.

Increased resource allocation

C.

Increased schedule variance

D.

Increased labor cost

E.

Increased labor overhead

Full Access
Question # 78

Company A recently partnered with Company B. Over the past few months, multiple teams have been working to refine internal processes to deliver products in a more timely manner.

If the effort is successful, which of the following will MOST likely occur?

A.

Reorganization

B.

Relocation

C.

Outsourcing

D.

Demerger

Full Access
Question # 79

A project manager receives an initial project assignment.

Which of the following documents is MOST likely to indicate the organizational structure for the project?

A.

Communication management plan

B.

Baseline

C.

Business case

D.

Organizational breakdown structure

Full Access
Question # 80

On larger projects, a vendor may occasionally proceed upon receipt of the:

A.

ROE.

B.

RFI.

C.

NDA.

D.

LOI.

Full Access
Go to page: