New Year Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PK0-004 Exam Dumps - CompTIA Project +

Go to page:
Question # 25

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

A.

EAC

B.

BAC

C.

TCPI

D.

ETC

Full Access
Question # 26

A meeting has taken place with quality assurance tram members and the project manager.

Which of the following events would MOST likely have triggered the meeting?

A.

Audit

B.

Risk register update

C.

Task completion

D.

Resource change

Full Access
Question # 27

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

A.

Incident response

B.

Quality control

C.

Resource changes

D.

Business continuity response

Full Access
Question # 28

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

A.

Managing change

B.

Fast tracking

C.

Rolling wave planning

D.

Crashing

Full Access
Question # 29

During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

A.

12 days

B.

14 days

C.

16 days

D.

19 days

Full Access
Question # 30

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Full Access
Question # 31

Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?

A.

Work breakdown structure

B.

Milestone list

C.

Organizational chart

D.

Action items

Full Access
Question # 32

A vendor is not meeting the agreed-upon quality of deliverables. To try to renegotiate the contract with the vendor, which of the following documents should the project manager use to highlight the areas that need improvement?

A.

RFI

B.

SLA

C.

MOU

D.

LOI

Full Access
Go to page: