New Year Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PK0-004 Exam Dumps - CompTIA Project +

Go to page:
Question # 41

The final project report should contain which of the following?

A.

Minutes of all the project meetings

B.

Project design documentation

C.

Detailed breakdown of the schedule

D.

Summary of the project cost

Full Access
Question # 42

A project needs two more months of work to be completed, but the deadline is in 35 days. The project

manager heard the company recently hired an experienced person. The project manager scheduled a meeting

with the functional manager to negotiate bringing the experienced person to the team. Which of the following

strategies is the project manager trying to apply?

A.

Exploit

B.

Mitigate

C.

Accept

D.

Transfer

Full Access
Question # 43

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Which of the following represents the cost variance for both project completions?

A.

-$4.8K and -$7K

B.

-$4.9K and $7K

C.

$4.8K and -$7K

D.

$4.8K and $7K

Full Access
Question # 44

Which of the following should be included in an effective SOW?

A.

Lessons learned

B.

Procurement process

C.

Corrective action plan

D.

Project objectives

Full Access
Question # 45

Which of the following represents additional unauthorized requirements from the client?

A.

Scope creep

B.

Changing scope baseline

C.

Change request

D.

Gold plating

Full Access
Question # 46

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project

coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.

Which of the following resources has the authority to authorize this change?

A.

Stakeholders

B.

Scrum master

C.

Project sponsor

D.

Project team

Full Access
Question # 47

A politically sensitive project is being proposed. The sponsor decides to outsource the work despite having a highly capable team.

Which of the following BEST describes the risk mitigation strategy being used?

A.

Acceptance

B.

Avoidance

C.

Transference

D.

Exploitation

Full Access
Question # 48

An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?

A.

Language barrier

B.

Personal preference

C.

Technological factor

D.

Cultural difference

Full Access
Go to page: