Question # 4

A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits

and jeopardizes the commitment date.

Which of the following should the project manager do NEXT?

A.

Ask the functional manager to release the 20% of allocation from the secondary project.

B.

Ask the sponsor to negotiate with the project manager from the secondary project.

C.

Ask the PMO to assign additional resources.

D.

Ask the project manager of the secondary project to release the resource.

Full Access
Question # 5

The upper management team does not agree with certain aspects of a project. Which of the following would be the BEST way for the project manager to handle this situation?

A.

Talk to the project management office.

B.

Discuss the issue with the project sponsor.

C.

Hold a meeting with the project coordinator

D.

Brainstorm successful ideas with the project team.

Full Access
Question # 6

New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.

Which of the following is the BEST way for the PM to validate the assessment?

A.

Ask the team for estimates, and review the project schedule and budget.

B.

Ask the team to review the product scope and validate its impact on the schedule and quality.

C.

Ask the team for estimates, and review the cost management plan.

D.

Ask the team to perform a SWOT analysis, and validate the assessment.

Full Access
Question # 7

In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?

A.

The project is behind schedule

B.

The project is over budget

C.

The project has float available

D.

The project needs a gate review

Full Access
Question # 8

A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?

A.

Social media

B.

Email

C.

Instant messaging

D.

Team meeting