Question # 9

Which is an objective of the quality review technique?

A.

To identify a product's quality criteria

B.

To provide assurance that the project is being conducted properly

C.

To assess that a product conforms to set criteria

D.

To ensure that staff are properly trained in the quality methods

Full Access
Question # 10

Which is a purpose of the Quality theme?

A.

Establish how the project will ensure that all products created meet their requirements

B.

Establish quality assurance to maintain the quality management system

C.

Identify all the products of the project to ensure the scope has been adequately defined

D.

Determine the communication needs of the organization's quality assurance function

Full Access
Question # 11

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Full Access
Question # 12

Which statement applies to Stage Plans?

A.

Always have the same duration as the Project Plan

B.

Are produced at the same time as the Project Initiation Documentation

C.

Assist the Project Manager in the day-to-day running and control of the project

D.

Provide a baseline against which the Project Board monitor overall progress

Full Access
Question # 13

When should the Project Board refer to corporate or programme management for a decision?

A.

The stage requires resources

B.

It is forecast that project level tolerance will be exceeded

C.

The Senior Supplier or Senior User needs to be changed

D.

Any request for change needs to be approved

Full Access
Question # 14

Which is created during the Starting up a Project process?

A.

Project mandate

B.

Project management team role descriptions

C.

Communication Management Strategy

D.

Quality Register

Full Access
Question # 15

Which is a purpose of a Risk Register?

A.

Capture risks that may occur during the project

B.

Record how risk management activities will be undertaken on the project

C.

Record the risk tolerance for the project

D.

Capture issues which are impacting on the delivery of the project objectives

Full Access
Question # 16

Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

A.

Change

B.

Plans

C.

Progress

D.

Risk

Full Access