Question # 9

Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?

A.

Expenditure Types

B.

Project Templates

C.

Work Type

D.

Project Types

E.

Project Class Categories

Full Access
Question # 10

Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.

Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

A.

Daily Spread Basis

B.

Back Loaded

C.

Bell Curve

D.

S-Curve

E.

Even

Full Access
Question # 11

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

A.

USD 184

B.

USD 120

C.

USD 134

D.

USD 70

Full Access
Question # 12

Which three can be tracked as Status tracking for Project Invoice Approval Notifications? (Choose three.)

A.

Person assigned for approval

B.

Prior actions

C.

Pre-approval activities

D.

Date-wise updates to the document

E.

Persons with whom it is still pending approval

Full Access
Question # 13

You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that these distribution set lines are not validated against the project transaction controls and you are allowed to save it without any validation errors. Identify the reason why the project transaction controls are not applied. (Choose the best answer.)

A.

There is no expenditure type information available on the distribution set line.

B.

There is no expenditure organization information available on the distribution set line.

C.

There is no expenditure item date information available on the distribution set line.

D.

The account code combination is not available on the distribution set line.

Full Access
Question # 14

Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?

A.

Manage Project Type page

B.

Manage Capitalized Interest Rate Schedules page

C.

Manage Capitalized Interest Rates page

D.

Manage Expenditure Type page

E.

Manage Project Plan Type page

Full Access
Question # 15

You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)

A.

Exceptions

B.

Accounting Calendar

C.

Workday Patterns

D.

Time Off

E.

Expenditure Type

Full Access
Question # 16

Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.

Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)

A.

The current period start date is used for calculating labor demand for the current year.

B.

The current date is used for calculating labor demand for the current year.

C.

The project start date of Jan-2015 was used for calculating labor demand, and hence it calculated the demand for the year 2015.

D.

The date entered by a user as a parameter when running the Update EPS job was set to 01-Jan-2015, and hence the calculations show results for the year 2015.

Full Access