Question # 89

Which tools or techniques are used in the Plan Schedule Management process?

A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Full Access
Question # 90

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 91

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Full Access
Question # 92

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Question # 93

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Full Access
Question # 94

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Full Access
Question # 95

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Full Access
Question # 96

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

Full Access