Question # 25

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Full Access
Question # 26

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 27

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Full Access
Question # 28

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Full Access
Question # 29

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Full Access
Question # 30

The scope management plan is a subsidiary of which project document?

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Full Access
Question # 31

The stakeholder register is an output of:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Full Access
Question # 32

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Full Access