Question # 9

Based on the SAP Activate methodology, which of the following tests are formal, and therefore must be documented during implementation? Note: There are 2 correct answers to this question.

A.

Business process test

B.

String test

C.

Unit test

D.

Integration test

Full Access
Question # 10

What triggers a goods issue for scrapping in SAP Best Practice Warehouse Ad Hoc Goods Issue (3BT)?

A.

An outbound delivery

B.

A material document

C.

A posting change

D.

A material reservation

Full Access
Question # 11

Besides the SAP Fiori app Create Posting Changes which other app allows you to run the warehouse posting changes process?

A.

Process Warehouse Tasks - Picking

B.

Post Goods Movement

C.

Create Product Warehouse Tasks

D.

Warehouse Monitor

Full Access
Question # 12

In the SAP standard scenario SAP EWM Integration – Outbound Processing to Customer (2VK), which document is created in SAP S/4HANA Cloud Warehouse Management and replicated in the SAP EWM system?

A.

Stock transport order

B.

Goods issue posting

C.

Outbound delivery

D.

Warehouse order

Full Access
Question # 13

In SAP Best Practice SAP EWM Integration - Customer Returns (2VO), which activities are carried out in the SAP EWM system? Note: There are 2 correct answers to this question.

A.

Create a material document

B.

Post a goods receipt

C.

Create a return delivery

D.

Create a posting change

Full Access
Question # 14

When are batches created during the Warehouse Inbound Processing scenario (3BR)? Note: There are 2 correct answers to this question.

A.

At the inbound warehouse task creation

B.

At the inbound warehouse task confirmation

C.

When posting the goods receipt for the inbound delivery

D.

Manually before inbound delivery processing

Full Access
Question # 15

When are the finished goods packed onto handling units in SAP Best Practice SAP EWM Integration - Delivery-Based Production Integration (2VM)?

A.

When processing the expected goods receipt document in SAP S/4HANA Cloud

B.

After the confirmation of the putaway tasks in SAP EWM

C.

After the goods receipt for the inbound delivery is posted in SAP EWM

D.

When the packing operation in the production order is confirmed in SAP S/4HANA Cloud

Full Access
Question # 16

What determines the set of data migration objects available from the Migrate Your Data application?

A.

The selected source system

B.

The selected target fields

C.

The selected business scenarios

D.

The customer legacy system

Full Access