Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

Note! Following C_TS412_1909 Exam is Retired now. Please select the alternative replacement for your Exam Certification. The new exam code is C_TS412_2021

C_TS412_1909 Exam Dumps - SAP Certified Application Associate - SAP S/4HANA Project Systems

Go to page:
Question # 4

How are earliest dates and latest dates of activities scheduled?

A.

Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates

B.

Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling

C.

Earliest dates and latest dates are scheduled by forward scheduling

D.

Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling

Full Access
Question # 5

The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?

A.

Free planning

B.

Top-down

C.

Strict bottom-up

D.

Bottom-up

Full Access
Question # 6

Resources

How are capacity requirements determined?

A.

Independent of scheduling and according to the capacity planner group.

B.

Using scheduling and the capacity category.

C.

Using the control key of an activity.

D.

Using scheduling and distribution key.

Full Access
Question # 7

Which statement is valid regarding networks?

A.

A network activity can be assigned to several WBS elements

B.

Material components can be assigned to activity elements

C.

Relationships can be used to connect activities of different networks

D.

A network can be activity-account-assigned and header-account-assigned

Full Access
Question # 8

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

A.

An activated Scheduling indicator in the control key of the internal processing activity

B.

Whether the work for the internal activity is greater than its duration

C.

The unit (for example, hour, day) of the field Normal Duration field of the activity

D.

The relationships between activity elements

E.

The factory calendar in the work center used for the internal processing activity

Full Access
Go to page: