Question # 25

A newer automotive supplier has not fully developed its information technology (IT) systems. The supplier has Just received a contract from a large automotive manufacturer which requires the supplier to use electronic data interchange (EDI) transactions for receiving orders, sending advance ship notices (ASNs), and receiving invoice payments. What strategy can the supplier adopt to immediately meet the EDI requirements?

A.

Select, install, and implement EDI software.

B.

Use current third-party logistics provider (3PL) to handle the EDI transactions.

C.

Claim hardship and ask the automotive manufacturer for a waiver.

D.

Negotiate using email as an alternative with the customer.

Full Access
Question # 26

Which of the following conditions is most likely to result in planned production that is greater than the total demand over the sales and operations planning (S&OP) horizon for a product family that is

made to stock?

A.

An increase in the customer service level is planned for the product family.

B.

New models are being added to the product family.

C.

Planned ending inventory for the product family is less than the beginning inventory.

D.

There is a long-term upward trend in demand for the product family.

Full Access
Question # 27

An example of an assignable cause of variation in process performance is:

A.

power fluctuation during machine operation.

B.

machine vibration during operation.

C.

incorrect setup of a machine by the operator.

D.

changes in temperature in the machine shop.

Full Access
Question # 28

When designing a production cell, which of the following items would be the most important consideration?

A.

Theunit per hour requirement for the production cell to meet the sales forecast

B.

Theflow of materials into the cell and sequencing of operations to minimize total cycle time

C.

Theoutput rate for the first operation and move time after the last workstation

D.

Thetakt time requirement for each operator to meet the monthly production goals of theplant

Full Access
Question # 29

The question below is based on the following standard and actual data of a production order

Which of the following statements about variances is true?

A.

The material price vanance for Component A is favorable by S10

B.

The labor pnce variance is unfavorable by S20

C.

The material usage variance for Component B is favorable by $36

D.

The labor efficiency variance is favorable by S20

Full Access
Question # 30

Forecast error typically triggers forecast revision when it is:

A.

used in computing the tracking signal.

B.

associated with the Introduction stage of the product life cycle.

C.

continually increasing.

D.

caused by random variation.

Full Access
Question # 31

If all other factors remain the same, when finished goods inventory investment is increased, service levels typically will:

A.

remain the same.

B.

increase in direct (linear) proportion.

C.

increase at a decreasing rate.

D.

increase at an increasing rate.

Full Access
Question # 32

Global outsourcing and shared suppliers serving an industry are drivers of which category of risk?

A.

Supply disruptions

B.

Forecast inaccuracy

C.

Procurement problems

D.

Loss of intellectual property

Full Access