Question # 9

Which of the following is NOT considered a prevention cost?

A.

Writing operating procedures.

B.

Training.

C.

Data acquisition and analysis.

D.

Calibrating test equipment.

Full Access
Question # 10

Of the services listed below, which one performed by design engineering is of particular interest to QA personnel?

A.

Audit reports.

B.

Cost reports.

C.

Change action.

D.

Rework criteria.

Full Access
Question # 11

Which of the following is the BEST statement to make regarding the relationship between product precision and product production?

A.

With too little precision, production costs increase.

B.

With too much precision, production costs increase.

C.

Precision costs and performance are related.

D.

With little precision, performance will improve.

Full Access
Question # 12

Which of the following are TRUE statements regarding the use of visual inspection?

â… . Reference standards can be used.

â…¡. It provides consistency between inspectors.

â…¢. It is relatively expensive.

â…£. It can be quickly performed.

A.

I andIVonly

B.

I,IIandIVonly

C.

IIandIVonly

D.

I,II,IIIandIV

Full Access
Question # 13

The value for t, when making a two-tailed paired t test, with samples of 13 and alpha =0.05, is

A.

1.782

B.

2.179

C.

2.064

D.

1.711

Full Access
Question # 14

Select the incorrect statement from among the following. The IDs of a certain piece of tubing are normally distributed with mean 1.00". The proportion of tubing with IDs less than 0.90 is

A.

Less than the proportion of Ids greater than 0.90

B.

Less than 50 percent.

C.

Less than the proportion with IDs greater than 1.10

D.

Less than the proportion with IDs greater than 1.00

Full Access
Question # 15

Which of the following tools can provide a ranking of things to be done?

A.

Measles charts.

B.

Cause & effect diagram.

C.

Scatter diagram.

D.

Checklist.

Full Access
Question # 16

What percentage of the area under the standard normal curve is included within (+/-) 1.5 standard deviations from 0?

A.

0.8664

B.

0.7500

C.

0.6680

D.

0.9332

Full Access