Question # 4

SCENARIO 1

DreamPartner dating agency are redesigning their dating application following a major security breach in which sensitive customer data was made publically available. The redesign includes stronger security encryption and performance tuning.

The product risk register for the redesign project, which was produced after all requirements had been agreed, includes the following:

The organisational Test Strategy contains the following objectives:

1. A Risk-based lest approach must be adopted for all projects

2. Functional regression testing should start as soon as functional testing is complete

3. Automated tests may be run before or in parallel with manual tests

The project Test Plan has allocated 6 weeks to complete all test execution, with functional testing taking 3 weeks to execute, performance and security testing 2 weeks each and regression testing 1 week.

Which of the following options places the test suites (TS1 to TS5) in the correct order for test execution?

SELECT ONE OPTION

A.

TS3, TS1, TS2, TS5, TS4.

B.

TS1, TS2, TS5, TS3, TS4.

C.

TS3, TS4, TS1, TS2, TS5.

D.

TS5, TR1, TS3 TSA, TS2

Full Access
Question # 5

How might test monitoring and reporting differ for a project using a SCRUM development model rather than a V-model?

A.

A move to milestone-based reporting, with optional automated dashboards

B.

Responsibility for test monitoring and reporting lies with the Product Owner, rather than the test manager

C.

Reports are produced on a continuous basis with real-time dashboards and daily status updates

D.

Monitoring is more informal with less need for regular status reports

Full Access
Question # 6

Which of the following are primary activities in conducting product risk analysis? [1]

A.

Risk testing, risk management

B.

Risk identification, risk assessment

C.

Risk identification, risk testing

D.

Risk management, risk assessment

Full Access
Question # 7

Which combination matches the four cost of quality categories with a CORRECT example of its category?

A.

a4, b3, c1, d2

B.

a3, b1, c2, d4

C.

a2, b4, c3, d1

D.

a1, b2, c4, d3

Confirmation testing at the system test level

Deploying an emergency fix to production

Designing functional suitability tests

Strengthening recruitment criteria for technical architects

Full Access
Question # 8

Test results are reported as "Requirements tested, passed, and failed".

What test strategy are you using? [1]

A.

Model-based

B.

Exploratory

C.

Analytical

D.

Reactive

Full Access