Question # 9

Testing Process

The following are the exit criteria described in the test plan of a software product:

EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).

EX2. All test cases in the test suite must be run during the execution phase.

EX3. Defects are classified into two categories: “C” (critical defect) and “NC” (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.

Which of the following information is useless when the specified exit criteria is evaluated?

Number of correct responses: 1

K21 credit

A.

A traceability matrix showing the relationships between the product risk items and the test cases

B.

A list of all the open defects with the associated classification information extracted from the defect tracking system

C.

A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system

D.

The execution status of all the test cases extracted from the test management tool

Full Access
Question # 10

The following is the unique “critical” quality risk item that has been identified:

CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user

Test analysis for system testing has just begun and the following test conditions have been identified:

TC-SEL-2. Test the selection of the package sizes

TC-SEL-4. Test wrong numbers of bottles for an order

TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user

Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.

Which of the following is a positive logical test that is complete and correct, and covers the REQ-SEL-4 requirement?

Number of correct responses: 1

K32 credits

A.

Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed

B.

Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed

C.

Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed

D.

Select a 6-bottles package, then try to insert 7 bottles

Full Access
Question # 11

Which of the following is a factor that is likely to increase the test estimate? [1]

A.

Use of a new technology

B.

A requirement for high level test documentation

C.

Assigned personnel who are experienced on working with similar projects in similar environments

D.

Static test data

Full Access
Question # 12

The test team is using a distributed model for testing.

What is the primary factor you should consider with this model? [1]

A.

Alignment of methodologies

B.

Co-location of test team

C.

Provision of growth opportunities for the individual testers

D.

Planned vs. actual hours

Full Access
Question # 13

Your Project Manager has challenged you to come up with a process improvement strategy using the IDEAL model.

Which step within the process defines the success criteria? [2]

A.

Entrance

B.

Analysis

C.

Diagnosing

D.

Initiation

Full Access
Question # 14

Which of the following organizational structures would be considered unorthodox? [1]

A.

Developers within the same team unit test each others' code prior to handing over to a separate testing team for system testing

B.

Developers and testers are integrated within the same project team, each role focusing on a different level of testing

C.

After developers are done unit testing, business analysts alpha test the system before handing over to a separate testing team for system testing

D.

DBAs confirm the referential integrity of the database and developers complete their unit testing before handing over to

external organization for system testing

Full Access
Question # 15

Your test team has created a custom automation tool that will be used for an upcoming release. Now that the tool has been coded, what

should be the next step? [1]

A.

Create the tool support guide

B.

Perform an ROI study

C.

Compare the new tool to open source tools

D.

Test the tool

Full Access
Question # 16

Improving the Testing Process

Which of the following statements about the STEP test process improvement model is true?

Number of correct responses: 1

K21 credit

A.

In the STEP model, tests validate the requirements and use cases when they are developed

B.

The STEP model stresses defect detection and demonstration of capability, whereas the defect prevention is a secondary potential goal of testing

C.

The STEP model assures that the system requirements specification and the test design specification processes don't overlap

D.

In the STEP model, testware design occurs after coding

Full Access
Go to page: