Question # 4

Identify the correspondences between the aspects (listed from 1 to 4) and factors to be considered(listed from A to D) when selecting performance testing tools.

1.Compatibility.

2.Scalability.

3.Understandability.

4.Monitoring.

1.Level of technical knowledge needed to use the tool.

2.Correlation of the monitoring with the defined transactions.

3.Protocols.

4.Ability to generate load from multiple points of presence.

SELECT ONE OPTION

A.

1C-2D-3A-4B.

B.

1B-2D-3A-4C.

C.

1D-2C-3A-4B.

D.

1C-2D-3B-4A.

Full Access
Question # 5

In which activity of the testing process is the scope of performance testing established?

SELECT ONE OPTION

A.

Test analysis.

B.

Test design.

C.

Test planning.

D.

Test monitoring and control.

Full Access
Question # 6

(REFER TO BASE SCENARIO 2): When you refer to Base Scenario 2, you are referring to the description and only the description, without any modification.

Question specific constraints: (specific constraints are not part of the Base Scenario and are specific to this question).

Throughout the month of January (31 days), the company performed 3,100 departure operations from the Capital City Airport. These departure operations transported 465,000 passengers during the hours of operation, from 07:00 to 23:00.

The departing passengers (one of the most relevant operational profiles) will access the front-end of the application to check in for their flight. It is known that 30% of departing passengers reconnect after checking in to request the boarding pass to be resent or printed.

Question

How many departing passengers access the front-end only once to check in per hour?

SELECT ONE OPTION

A.

187.50 departing passengers / hour

B.

1,218.75 departing passengers / hour.

C.

625.00 departing passengers / hour.

D.

812.50 departing passengers / hour.

Full Access
Question # 7

Which ONE of the following mechanisms is used to make the load test represent a load situation in a real production environment?

SELECT ONE OPTION

A.

Generate load through the Application Programming Interface (API).

B.

Configure environments with multiple points of presence.

C.

Generate load through the User Interface.

D.

Gradually restrict system resources during the load test.

Full Access
Question # 8

(REFER TO BASE SCENARIO 2): When you refer to Base Scenario 2, you are referring to the description and only the description, without any modification.

Question specific constraints: (specific constraints are not part of the Base Scenario and are specific to this question).

Throughout the month of January (31 days), the company performed 3,100 departure operations from the Capital City Airport. These departure operations transported 465,000 passengers during the hours of operation, from 07:00 to 23:00.

The departing passengers (one of the most relevant operational profiles) will access the front-end of the application to check in for their flight. It is known that 30% of departing passengers reconnect after checking in to request the boarding pass to be resent or printed.

Question

How many departing passengers access the front-end per hour?

SELECT ONE OPTION

A.

625.00 departing passengers / hour.

B.

1,425.00 departing passengers / hour

C.

1,700 00 departing passengers / hour.

D.

812.50 departing passengers / hour.

Full Access
Question # 9

Choose the VALID description of the ramp-up concept.

SELECT ONE OPTION

A.

Stage of reaching the stationary state.

B.

Stage of finishing the test.

C.

Stage of exit from a stationary state by increasing the number of concurrent users.

D.

Technique in which the load on the system is increased to a certain value in the shortest possible time.

Full Access
Question # 10

(REFER TO BASE SCENARIO 2): When you refer to Base Scenario 2, you are referring to the description and only the description, without any modification.

Question specific constraints: (specific constraints are not part of the Base Scenario and are specific to this question).

• Natalie should make a presentation to the technical stakeholders In order to explain the performance test plan.

Question

Which ONE of the following options contains information that should be included in Natalie's presentation to the technical stakeholders?

SELECT ONE OPTION

A.

A spike test shall be conducted in a test environment equivalent to the production environment. Passengers shall be removed from the production environment, disassociated and Imported into the test environment.

B.

A spike test shall be conducted in the performance test environment set up by the systems manager. Preparation includes installation from the clone of the virtual machine identified for this purpose.

C.

The cost of the spike test will be In line with the budget submitted by the cloud service provider. The test must take place within the planned timeframe and use the disassociation algorithm previously agreed.

D.

A performance test will be conducted to verify the management application s capability to support simultaneous, i.e. concurrent, request peaks. The objective is to check that the system will be able to support the operations.

Full Access
Question # 11

Inwhich activity of the testing process are specific test conditions identified for performance testing?

SELECT ONE OPTION

A.

Test planning.

B.

Test monitoring and control.

C.

Test analysis.

D.

Test design.

Full Access
Question # 12

Refer to Base Scenario 1: When you refer to Base Scenario 1, you are referring to the description and only the description, without any modification.

Question specific constraints: (specific constraints are not part of the Base Scenario and are specific to this question).

•The project follows an iterative and Incremental development life cycle model.

•Development approach: Agile.

Question

Which of the statement(s) below is (are) TRUE regarding how the performance test is undertaken7

1.The performance test can have a dedicated iteration in a specific way.

2.Performance testing should be performed in a cloud-based performance test environment

3.The performance test may be conducted by a specific team.

4.A performance test cycle must be performed in each iteration by the development team (Agile).

SELECT ONE OPTION

A.

True statements: IV.

B.

True statements: III, IV.

C.

True statements: II, III.

D.

True statements: I, III.