In addition to tasks dependencies, how can you specify a delay between tasks?
with Slack Time in days or hours
with Start Delay time in days or hours
with Start-to-Start time in hours
None of these
Your project has a task called Create Student Guide (Task #3) which CANNOT start until Review Course Outline (Task #2) finishes. What is the correct dependency code?
2:FS on Create Student Guide
2:SF on Create Student Guide
3:FS on Review Course Outline
3:FF on Review Course Outline