Question # 17

Della works as a security manager for SoftTech Inc. She is training some of the newly recruited personnel in the field of security management. She is giving a tutorial on DRP. She explains that the major goal of a disaster recovery plan is to provide an organized way to make decisions if a disruptive event occurs and asks for the other objectives of the DRP. If you are among some of the newly recruited personnel in SoftTech Inc, what will be your answer for her question? Each correct answer represents a part of the solution. Choose three.

A.

Protect an organization from major computer services failure.

B.

Minimizethe risk to the organization from delays in providing services.

C.

Guarantee the reliability of standby systems through testing and simulation.

D.

Maximize the decision-making required by personnel during a disaster.

Full Access
Question # 18

Which of the following is a set of exclusive rights granted by a state to an inventor or his assignee for a fixed period of time in exchange for the disclosure of an invention?

A.

Patent

B.

Utility model

C.

Snooping

D.

Copyright

Full Access
Question # 19

Joseph works as a Software Developer for Web Tech Inc. He wants to protect the algorithms and the techniques of programming that he uses in developing an application. Which of the following laws are used to protect a part of software?

A.

Code Security law

B.

Trademark laws

C.

Copyright laws

D.

Patent laws

Full Access
Question # 20

Which of the following security models focuses on data confidentiality and controlled access to classified information?

A.

Bell-La Padula model

B.

Take-Grant model

C.

Clark-Wilson model

D.

Biba model

Full Access
Question # 21

You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

A.

Mitigation

B.

Sharing

C.

Acceptance

D.

Transference

Full Access
Question # 22

Which of the following is the process performed between organizations that have unique hardware or software that cannot be maintained at a hot or warm site?

A.

Cold sites arrangement

B.

Business impact analysis

C.

Duplicate processing facilities

D.

Reciprocal agreements

Full Access
Question # 23

Which of the following BCP teams is the first responder and deals with the immediate effects of the disaster?

A.

Emergency-management team

B.

Damage-assessment team

C.

Off-site storage team

D.

Emergency action team

Full Access
Question # 24

Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

A.

Quantitative analysis

B.

Contingency reserve

C.

Risk response

D.

Risk response plan

Full Access