Which risk response encourages collaboration on risk management activities?
Avoid
Reduce
Share
Prepare contingent plans
Which is the BEST definition of a stakeholder?
An individual, group or organization that can affect, or be affected by a programme
A member of a team that is formed to help its operational area through the change cycle
A member of the programme management team or project management team
An individual accountable for the success of the programme
In which situation should benefits management continue after programme closure?
Transition is still being undertaken
Business change managers are still facilitating change
The benefits still need to be aligned to corporate strategy
Unexpected benefits are still being captured
Which is a trigger for a compliance programme?
The corporate board has created a vision for change
A number of stand-alone projects would benefit from better coordination
The organization has to change to meet requirements of new legislation
The organization chooses to take a new innovative approach to product development
Which is an assurance management technique?
Issue management
Gated reviews
Quality management
Change control