Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
To use empiricism, based on knowledge that comes from experience
To build, measure, learn from your experiences
To create a minimum viable product to manage uncertainty
To fail fast, if you are going to fail
When should PRINCE2 Agile be used?
When a team is created to deliver a specific product
When delivering an ongoing service to a customer
When an established team performs product maintenance
When simple requests to update a product are implemented
During which process should release planning be done for the FIRST time?
Initiating a project
Managing a stage boundary
Managing product delivery
Controlling a stage
Which role is responsible for facilitating the Agilometer assessment?
Project board
Project manager
Team manager
Customer subject matter expert
Which statement about the ‘protect the level of quality’ target is CORRECT?
It is achieved by allowing enough time for testing
It is achieved by using the same team members
It gives confidence on the progress of the project
It delivers the early realization of benefits