Completed by a Single Agile Release Train within one PI:
Definition:A Feature in SAFe is a service or functionality that meets the needs of a customer and can be delivered within a single Program Increment (PI) by an ART.
Explanation:Features are planned and delivered within the timeframe of a PI, ensuring that they provide tangible value and align with the ART's objectives.
Prioritized using Weighted Shortest Job First (WSJF):
Definition:WSJF is a prioritization method used in SAFe to sequence work for maximum economic benefit.
Explanation:Features are prioritized based on their cost of delay and the effort required to implement them. This ensures that the most valuable and impactful features are delivered first.
SAFe Scrum Master References:
SAFe framework details the concept of Features, emphasizing their completion within a PI and their prioritization using WSJF to maximize value delivery.
Question # 18
What is the purpose of the Scrum of Scrums meeting during PI Planning?
The Scrum of Scrums meeting during PI Planning is designed to identify and manage dependencies across teams. This meeting allows representatives from each team to come together and discuss how their plans intersect and where they might impact each other.
Dependency Identification:Teams identify dependencies early to manage risks and align their efforts.
Coordination:Facilitates better coordination and integration of work between multiple teams.
Communication:Provides a forum for raising issues and ensuring that all teams are aware of potential impacts on their work.
This helps in creating a more cohesive and integrated approach to delivering the Program Increment (PI).
SAFe Scrum Master References:
SAFe Advanced Scrum Master Training Material, Chapter on PI Planning​​