Question # 9

What is the purpose of documenting the 'Measurement methodology' in a change communication strategy?

A.

Assess the effectiveness of the communication efforts.

B.

Communicate test activities for the final solution.

C.

Quantify the number of people impacted by the change.

D.

Ensure everyone understands the value of the change.

Full Access
Question # 10

What kind of power is conveyed by a manager who is admired and respected by their subordinates and seen as a role model?

A.

Legitimate.

B.

Reward.

C.

Coercive.

D.

Referent.

Full Access
Question # 11

According to Tuckman, in what stage of the team development model will members of the team be 'working collectively to achieve results'?

A.

Forming.

B.

Storming.

C.

Adjourning.

D.

Performing.

Full Access
Question # 12

Which of the following are recognized DSDM styles of Timebox?

1. Unstructured

2. Consolidated

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Full Access
Question # 13

When using the Iterative Development technique, which of the following should each cycle include?

1. Though

2. Action

3. Control

4. Conversation

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Full Access
Question # 14

According to Tuckman, in what stage of the team development model are team members likely to want to test and challenge assumptions?

A.

Forming.

B.

Storming.

C.

Performing.

D.

Adjourning.

Full Access
Question # 15

Which information is given in the Solution Architecture Definition?

A.

A high-level design framework for the solution.

B.

A snapshot of the evolving business, solution and management products

C.

The tools and standards to be used in Evolutionary Development

D.

The strategy for testing

Full Access
Question # 16

Who is responsible for the application of Principle 8, Demonstrate Control?

A.

Collectively applied by the whole team

B.

The project-level roles

C.

Team Leader

D.

Project Manager

Full Access