Question # 17

Which should always be the first step in the Continuous Change Management Cycle?

A.

Ideas.

B.

Prioritization.

C.

Discovery.

D.

Action.

Full Access
Question # 18

Which of the following statements about diverse teams are true?

    Provide greater creativity.

    Reach consensus sooner than teams of 'similars.'

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Full Access
Question # 19

In a free format Timebox, when should reviews take place?

A.

During the Kick-Off phase

B.

Throughout the body of the Timebox.

C.

During the Close.Out phase

D.

After the Timebox has been completed

Full Access
Question # 20

Which is a factor used in the 'change formula' (Beckhard and Harris)?

A.

Level of dissatisfaction with the status quo.

B.

Expected return on investment and benefits.

C.

The quality of the leadership.

D.

Elapsed time it will take to achieve the change.

Full Access
Question # 21

According to the brain science of resistance, which of the key neural factors is an example of a fixed mindset?

A.

Routine seeking.

B.

Emotional reaction to forced change.

C.

Cognitive rigidity.

D.

Short-term focus.

Full Access
Question # 22

When is a Timebox Plan updated?

A.

At the Daily Start-ups

B.

At Timebox Kick-ups

C.

As needed by the Project Manager

D.

Each time a Timebox is completed

Full Access
Question # 23

Which of the following statements about a communication plan are true?

    Same overall format for all change initiatives.

    Content will differ depending on the scale and complexity of change.

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Full Access
Question # 24

How is contingency typically managed in a DSDM project?

A.

Not needed in a DSDM project.

B.

Allowed adding a percentage to the high-level estimates.

C.

Managed by varying the features to be delivered.

D.

Managed by varying time and cost

Full Access