Question # 9

Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.

A.

Quality gate checklist and quality gate guide

B.

Business-Driven Configuration questionnaire

C.

Test plan document

D.

Requirements feature in SAP Cloud ALM

Full Access
Question # 10

Which of the following characteristics relate to the Focused Build for SAP Solution Manager Functionality? Note: There are 2 correct answers to this question.

A.

SAP delivers a standard solution without any additional coding required.

B.

SAP delivers a standard solution with its own separate license.

C.

SAP delivers all configuration values within your project.

D.

SAP delivers all knowledge required with the solution.

Full Access
Question # 11

Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question.

A.

SAP Focused Run

B.

Focused Build for SAP Solution Manager

C.

SAP Cloud ALM

D.

Focused Insights for SAP Solution Manager

Full Access
Question # 12

How do you set up Scrum teams? Note: There are 2 correct answers to this question.

A.

As a cross-functional team covering multiple functions, like configuration, data loads, and testing.

B.

By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.

C.

Based on group size, but a minimum of 12 people.

D.

Based on end-to-end processes like order-to-cash.

Full Access
Question # 13

What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.

A.

Estimate the backlog user stories.

B.

Define objectives for each release.

C.

Analyze the functional and technical dependencies between user stories.

D.

Prioritize backlog user stories by business priority.

Full Access
Question # 14

When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?

A.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

B.

Realize phase scope, planning, and budget should be completed and final.

C.

User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.

D.

Release plan and sprint ceremony guidelines should be finalized.

Full Access
Question # 15

Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation? Note: There are 2 correct answers to this question.

A.

Create, review, and sign off the Project Charter.

B.

Discuss the benefits and functionality of SAP Analytics Cloud.

C.

Create, review, and sign off the Project Management Plan.

D.

Discuss the benefits of SAP Data Warehouse Cloud.

Full Access
Question # 16

For which of the following products do you find a specific set of SAP Best Practices for the public sector?

A.

SAP S/4HANA

B.

SAP SuccessFactors Employee Central

C.

SAP S/4HANA Cloud, public edition

D.

SAP Ariba Supplier Management

Full Access