Question # 17

What are the different views available for capacity planning and work center planning?

There are 2 correct answers to this question.

Response:

A.

Work center view

B.

Capacity planning view

C.

Periodic view

D.

Project view

Full Access
Question # 18

Which of the following cost planning transactions are related to Account assignment?

There are 3 correct answers to this question.

Response:

A.

Invoice posting

B.

Goods movement

C.

Confirmations

D.

Purchase requisitions

Full Access
Question # 19

An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?

Please choose the correct answer.

Response:

A.

Activity analysis tool

B.

Relationship analysis tool

C.

Cycle analysis tool

D.

Loop analysis tool

Full Access
Question # 20

You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...

There are 2 correct answers to this question.

Response:

A.

... basic dates of WBS elements are determined automatically.

B.

... the networks determine the schedule.

C.

... strict bottom-up planning is selected as the planning method.

D.

... forward scheduling is selected as the scheduling type.

E.

... the work breakdown structure determines the schedule.

Full Access
Question # 21

Where can you define that a network is a "header-account assigned" or "activity-account assigned"?

A.

Network profile

B.

Parameters for the network type

C.

Project profile

D.

Network type

Full Access
Question # 22

While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?

Please choose the correct answer.

Response:

A.

Scheduling forwards

B.

Scheduling backwards

C.

Variances

D.

Scheduling baseline, planned and forecast

Full Access
Question # 23

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?

Please choose the correct answer.

Response:

A.

Contractual management

B.

Claim management

C.

Claim Planning

D.

Variance management

Full Access
Question # 24

How can material components be assigned to network activities?

There are 3 correct answers to this question.

Response:

A.

By assigning them manually

B.

Using the bill of materials transfer

C.

Using assigned sales orders

D.

Using ProMan

E.

Using the Internet-based catalog

Full Access