What are the three tables that are defined for order type in network costing?
There are 3 correct answers to this question.
Response:
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?
There are 2 correct answers to this question.
Response:
Which of the following type determines which type of orders a system can create during assembly processing?
Please choose the correct answer.
Response:
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:
The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following?
There are 2 correct answers to this question.
Response:
All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are;
There are 3 correct answers to this question.
Response:
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?
Please choose the correct answer.
Response:
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.
Response:
What are the different views available for capacity planning and work center planning?
There are 2 correct answers to this question.
Response:
Which of the following cost planning transactions are related to Account assignment?
There are 3 correct answers to this question.
Response:
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?
Please choose the correct answer.
Response:
You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...
There are 2 correct answers to this question.
Response:
Where can you define that a network is a "header-account assigned" or "activity-account assigned"?
While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?
Please choose the correct answer.
Response:
Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:
How can material components be assigned to network activities?
There are 3 correct answers to this question.
Response: