Question # 4

What are some benefits of planning with planned independent requirements? Note: There are 2 correct answers to this question.

A.

Reduced production times

B.

Reduced delivery times

C.

Option to use make-to-order production

D.

Option to forecast planning for production resources

Full Access
Question # 5

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

A.

Increase the capacity supply in a time-phased interval.

B.

Determine a time period with available capacity on the planning board.

C.

Execute an infinite production planning run for the critical resources.

D.

Reduce the planning Window.

E.

Form optimum sequence to reduce setup times.

Full Access
Question # 6

In the Capacity Scheduling Table, which settings can you select for the planning strategy?

Note: There are 3 correct answers to this question.

A.

Finiteness level

B.

Fixed pegging

C.

Scheduling control

D.

Planning mode

E.

Direction

Full Access
Question # 7

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Full Access
Question # 8

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

A.

setup time

B.

Opening Period

C.

Float after Production

D.

Total replenishment lead time

Full Access