Question # 9

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Full Access
Question # 10

Under what circumstances can you change the material type for a material if stocks reservations or purchasing documents exist? Note: There are 2 correct answers to this question.

A.

The quantity value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Full Access
Question # 11

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Full Access
Question # 12

During production order creation several valid production versions are found. How does the system choose the production version?

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Full Access
Question # 13

You want to reduce planning efforts for B C classified materials. Which planning procedure do you recommend?

A.

Consumption Based Planning

B.

Subassembly Planning

C.

Advanced Planning

D.

Material Requirements Planning

Full Access
Question # 14

Why would you use phantom assemblies?

Note: There are 3 correct answers to this question.

A.

To simplify the structure of bills of material

B.

To reduce the number of changes required in bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To increase the number of planning levels

Full Access
Question # 15

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

A.

When several operations are maintained for one product

B.

When alternative resources are used within one operation

C.

When several production versions are maintained for one product

D.

When multiple planned orders are scheduled in parallel on one resource

Full Access
Question # 16

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.