which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Note: There are 2 correct answers to this question
Which materials have a negative quantity in a bill of material or in a recipe?
Note: There are 3 correct answers to this question
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?
Note: There are 2 correct answers to this question.
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run?
Note: there are 2 correct answers to this question.
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.
Note: there are 2 correct answers to this question.
Which business processes are affected by settings in the order-type-dependent parameters?
Note: There are 2 correct answers to this question.
How can you characterize dependent requirements in material requirements planning?
Note: There are 2 correct answers to this question.
Which time elements are relevant for lead time scheduling of a production order? Note:
There are 2 correct answers to this question.
Which of the following processes lead to an entry in the MRP planning file?
Note: There are 3 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.
What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question
Which standard item categories can you select inside a bill of material (BOM)?
Note: There are 2 correct answers to this question
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question
Which master data object governs the relationship between supply source and demand source in the Kanban process?
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
Note: There are 2 correct answers to this question