Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

C_TS422_2023 Exam Dumps - SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

Go to page:
Question # 4

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?

Note: There are 2 correct answers to this question.

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Orders (dispatched) chart

D.

Work center capacities chart

Full Access
Question # 5

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

A.

Execute an infinite production planning run for the critical resources.

B.

Reduce the planning time interval.

C.

Determine a time period with available capacity on the planning board.

D.

Increase the capacity supply in a timephased interval.

E.

Form optimum sequences to reduce setup times.

Full Access
Question # 6

What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.

A.

Reduced delivery times

B.

Reduced times for final assembly

C.

Option to forecast planning for production resources

D.

Option to use maketoorder production

Full Access
Question # 7

What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?

A.

The MRP run assumes external procurement.

B.

The MRP run assumes inhouse production.

C.

The MRP run plans the material only if a quotation has been maintained.

D.

The MRP run does NOT consider the material; it has to be planned interactively.

Full Access
Question # 8

You have maintained the parameters for simple discontinuation in the material master of a component.

Which business process will be affected if the available stock is zero the discontinuation date is in the past?

A.

Back flushing

B.

Kanban

C.

Material requirements planning

D.

Production order release

Full Access
Go to page: