Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

C_TS422_2023 Exam Dumps - SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

Question # 4

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?

Note: There are 2 correct answers to this question.

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Orders (dispatched) chart

D.

Work center capacities chart

Full Access
Question # 5

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

A.

Execute an infinite production planning run for the critical resources.

B.

Reduce the planning time interval.

C.

Determine a time period with available capacity on the planning board.

D.

Increase the capacity supply in a timephased interval.

E.

Form optimum sequences to reduce setup times.

Full Access
Question # 6

What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.

A.

Reduced delivery times

B.

Reduced times for final assembly

C.

Option to forecast planning for production resources

D.

Option to use maketoorder production

Full Access
Question # 7

What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?

A.

The MRP run assumes external procurement.

B.

The MRP run assumes inhouse production.

C.

The MRP run plans the material only if a quotation has been maintained.

D.

The MRP run does NOT consider the material; it has to be planned interactively.

Full Access
Question # 8

You have maintained the parameters for simple discontinuation in the material master of a component.

Which business process will be affected if the available stock is zero the discontinuation date is in the past?

A.

Back flushing

B.

Kanban

C.

Material requirements planning

D.

Production order release

Full Access
Question # 9

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Full Access
Question # 10

Under what circumstances can you change the material type for a material if stocks reservations or purchasing documents exist? Note: There are 2 correct answers to this question.

A.

The quantity value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Full Access
Question # 11

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Full Access
Question # 12

During production order creation several valid production versions are found. How does the system choose the production version?

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Full Access
Question # 13

You want to reduce planning efforts for B C classified materials. Which planning procedure do you recommend?

A.

Consumption Based Planning

B.

Subassembly Planning

C.

Advanced Planning

D.

Material Requirements Planning

Full Access
Question # 14

Why would you use phantom assemblies?

Note: There are 3 correct answers to this question.

A.

To simplify the structure of bills of material

B.

To reduce the number of changes required in bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To increase the number of planning levels

Full Access
Question # 15

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

A.

When several operations are maintained for one product

B.

When alternative resources are used within one operation

C.

When several production versions are maintained for one product

D.

When multiple planned orders are scheduled in parallel on one resource

Full Access
Question # 16

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Full Access
Question # 17

How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

A.

By capacity planning

B.

By order confirmation

C.

By order release

D.

By mass processing

Full Access
Question # 18

You are a consultant on an SAP S/4HANA Cloud brownfield project. In a meeting the customer decides to remodel an existing business process in accordance with clean core principles.

Which of the following SAP Signavio solutions can be used for the remodeling?

A.

SAP Signavio Process Insights

B.

SAP Signavio Process Intelligence

C.

SAP Signavio Process Governance

D.

SAP Signavio Process Manager

Full Access
Question # 19

You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?

A.

Specify a negative offset time.

B.

Specify a negative opening period.

C.

Specify a negative planning horizon.

D.

Specify a negative PP/DS horizon.

Full Access
Question # 20

What information do you have to maintain to define the relationship between supply source dem source in the Kanban process? Note: There are 2 correct answers to this question.

A.

Routing

B.

Work Center

C.

Replenishment strategy

D.

Production supply area

Full Access
Question # 21

Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

A.

Net requirements calculation is carried out for every sales order individually.

B.

Production orders are created with sales order reference.

C.

Storage location MRP areas are required for salesorderspecific stock.

D.

Both the reduction of maketoorder stock requirements occur on delivery.

E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Full Access
Question # 22

You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

A.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.

B.

Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.

D.

Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.

Full Access
Question # 23

What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

Quantity

B.

Status

C.

Installation point

D.

Scrap percentage

Full Access
Question # 24

You want to create a production order. What methods can you use?

Note: There are 2 correct answers to this question.

A.

Convert a purchase requisition

B.

Create without material

C.

Create by order release

D.

Create in Kanban process

Full Access