Question # 9

Which of the following master data can be used with process orders? (Choose three)

A.

Serial numbers

B.

Master recipes

C.

Resources

D.

Production/resource tools

E.

Production versions

Full Access
Question # 10

Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)

A.

Assign costing variants to order type.

B.

Propose a standard text key in work center.

C.

Assign a production scheduling profile to the material master (product).

D.

Enter formulas for costing in the work center.

E.

Use an operation control key with the indicator costing-relevant.

Full Access
Question # 11

Which of the following features are offered by MRP areas in SAP ECC? (Choose two)

A.

A storage location may be assigned to different MRP areas.

B.

An MRP area may include different storage locations.

C.

Make-to-order production is supported by storage location MRP areas.

D.

Subcontracting is supported by MRP areas.

Full Access
Question # 12

Which of the following elements can be used in a process order? (Choose three)

A.

Process instructions

B.

Parallel sequences

C.

Relationships

D.

Suboperations

E.

Phases

Full Access
Question # 13

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.

Which sequence category do you use to create the second sequence in the system?

A.

Finish-start relationship

B.

Standard sequence

C.

Parallel sequence

D.

Alternative sequence

Full Access
Question # 14

Which data forms the basis for calculating the capacity requirement for an operation?

(Choose three.)

A.

Standard values (routing)

B.

In-house production time (material master)

C.

Transport time (routing)

D.

Formulas (work center)

E.

Operation control key (routing)

Full Access
Question # 15

In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true?

(Choose two.)

A.

A consumption situation is dynamic and is always restructured with the planning run.

B.

Consumption can also take place between order reservations and planned independent requirements, depending on the strategy.

C.

Consumption always takes place on the material level between the planned independent requirements and the planned orders.

D.

The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Full Access
Question # 16

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.

What procedure would you recommend to the project team for setting the planning horizon on the system side?

A.

The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.

B.

The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.

C.

The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.

D.

The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

Full Access