Question # 4

Which functions can be triggered before releasing a production order? (Choose three)

A.

Selection of a routing

B.

Selection of a BOM

C.

Stock determination

D.

Confirmation

E.

Scheduling

Full Access
Question # 5

Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)

A.

Batch size optimization

B.

Midpoint scheduling

C.

Lot size optimization

D.

Finite capacity scheduling

E.

Setup time reduction

Full Access
Question # 6

Which of the following organizational efforts can be minimized using the KANBAN procedure?

A.

Effort for material staging

B.

Effort for capacity planning

C.

Effort for Sales and Operations Planning (SOP)

D.

Effort for master data maintenance

Full Access
Question # 7

For which of the following objects can you enter a confirmation? (Choose two)

A.

Work Center

B.

Production order operation

C.

Production order

D.

Trigger Point

Full Access
Question # 8

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).

Which of the following properties for the resulting dependent requirements applies?

A.

In multi-level backward scheduling, dependent requirements are calculated to the exact second.

B.

If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.

C.

When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

D.

In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

Full Access