Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

Note! Following C_TSCM42_67 Exam is Retired now. Please select the alternative replacement for your Exam Certification. The new exam code is C_TSCM52_67

C_TSCM42_67 Exam Dumps - SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7

Question # 4

Which functions can be triggered before releasing a production order? (Choose three)

A.

Selection of a routing

B.

Selection of a BOM

C.

Stock determination

D.

Confirmation

E.

Scheduling

Full Access
Question # 5

Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)

A.

Batch size optimization

B.

Midpoint scheduling

C.

Lot size optimization

D.

Finite capacity scheduling

E.

Setup time reduction

Full Access
Question # 6

Which of the following organizational efforts can be minimized using the KANBAN procedure?

A.

Effort for material staging

B.

Effort for capacity planning

C.

Effort for Sales and Operations Planning (SOP)

D.

Effort for master data maintenance

Full Access
Question # 7

For which of the following objects can you enter a confirmation? (Choose two)

A.

Work Center

B.

Production order operation

C.

Production order

D.

Trigger Point

Full Access
Question # 8

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).

Which of the following properties for the resulting dependent requirements applies?

A.

In multi-level backward scheduling, dependent requirements are calculated to the exact second.

B.

If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.

C.

When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

D.

In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

Full Access
Question # 9

Which of the following master data can be used with process orders? (Choose three)

A.

Serial numbers

B.

Master recipes

C.

Resources

D.

Production/resource tools

E.

Production versions

Full Access
Question # 10

Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)

A.

Assign costing variants to order type.

B.

Propose a standard text key in work center.

C.

Assign a production scheduling profile to the material master (product).

D.

Enter formulas for costing in the work center.

E.

Use an operation control key with the indicator costing-relevant.

Full Access
Question # 11

Which of the following features are offered by MRP areas in SAP ECC? (Choose two)

A.

A storage location may be assigned to different MRP areas.

B.

An MRP area may include different storage locations.

C.

Make-to-order production is supported by storage location MRP areas.

D.

Subcontracting is supported by MRP areas.

Full Access
Question # 12

Which of the following elements can be used in a process order? (Choose three)

A.

Process instructions

B.

Parallel sequences

C.

Relationships

D.

Suboperations

E.

Phases

Full Access
Question # 13

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.

Which sequence category do you use to create the second sequence in the system?

A.

Finish-start relationship

B.

Standard sequence

C.

Parallel sequence

D.

Alternative sequence

Full Access
Question # 14

Which data forms the basis for calculating the capacity requirement for an operation?

(Choose three.)

A.

Standard values (routing)

B.

In-house production time (material master)

C.

Transport time (routing)

D.

Formulas (work center)

E.

Operation control key (routing)

Full Access
Question # 15

In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true?

(Choose two.)

A.

A consumption situation is dynamic and is always restructured with the planning run.

B.

Consumption can also take place between order reservations and planned independent requirements, depending on the strategy.

C.

Consumption always takes place on the material level between the planned independent requirements and the planned orders.

D.

The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Full Access
Question # 16

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.

What procedure would you recommend to the project team for setting the planning horizon on the system side?

A.

The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.

B.

The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.

C.

The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.

D.

The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

Full Access
Question # 17

During the processing of production orders planned and actual costs are determined.

On which of the following objects can you collect these costs? (Choose two)

A.

Production order

B.

Product cost collector

C.

Work center

D.

Planned order

Full Access
Question # 18

The final assembly of a finished product should only be triggered when a customer order arrives.

Which planning strategy for the finished product do you use?

A.

Planning with make-to-stock (strategy 10)

B.

Planning at the assembly level (strategy 70)

C.

Planning without final assembly (strategy 50)

D.

Planning with final assembly (strategy 40)

Full Access
Question # 19

An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).

What is the easiest way to fulfill this requirement?

A.

Define a unit of measure group that converts pounds to kilograms in the basic data customizing and assign it to the material master on basic data view 1.

B.

Add a conversion factor for converting pounds to kilograms on basic data view 1 in the material master.

C.

Create a new material with a reference to the original material and assign the metric unit of measure to the new material master.

D.

There is no need to take any action. In this scenario, the conversion of units of measurements is done automatically.

Full Access
Question # 20

Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? (Choose three.)

A.

Master recipe-based manufacturing.

B.

Material requirements planning for production resources.

C.

Manufacturing without orders.

D.

Variable calculation of material quantities (product output, material usage).

E.

Manufacturing in charge quantities.

Full Access
Question # 21

What could be a consequence of confirming an operation?

A.

The planned costs are updated

B.

The capacity requirements are updated

C.

The production order is rescheduled

D.

The actual costs are settled

Full Access
Question # 22

Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.

Which BOM item category must you set to fulfill this requirement?

A.

D (document item)

B.

E (external procurement)

C.

M (phantom material)

D.

N (non-stock item)

Full Access
Question # 23

Which of the following functions does SAP Supply Chain Management (SCM) offer?

A.

Product development, safety, quality, and maintenance

B.

Planning of supply chains across company boundaries

C.

Communication with customers through different interaction channels

D.

Optimization of the procurement strategy with the supplier pool

Full Access
Question # 24

Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)

A.

Automatic generation of a transport order

B.

Material directory

C.

Pull list

D.

Pick list

E.

Logistics Information System (LIS)

Full Access
Question # 25

When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.

What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?

A.

Set up the planning file in Customizing and specify the plant parameters for plant 1000 in Customizing.

B.

Set up the planning files in Customizing and specify the plant parameters for plant 1000 in Customizing of the MRP group.

C.

Set up the planning file in Customizing and specify the plant parameters for plant 1000 in the MRP views in material master.

D.

Activate requirements planning in Customizing for MRP areas in plant 1000 and specify the plant parameters for plant 1000 in the MRP views in material master.

Full Access
Question # 26

What do you have to consider when you use SAP ECC long-term planning (LTP)? (Choose two)

A.

A planning scenario must be released before it can be used in LTP.

B.

Reorder point planned materials can be included in LTP.

C.

LTP focuses on the operational planning of important components.

D.

LTP creates purchase requisitions for external procurement.

Full Access
Question # 27

Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)

A.

Reorder point planned materials can be included in long-term planning.

B.

In case of external procurement, long-term planning creates purchase requisitions.

C.

A planning scenario must be released to use it in long-term planning.

D.

Long-term planning generally is operational planning of important components.

Full Access
Question # 28

Which property applies for consumption with planning strategy 40 (planning with final assembly)?

A.

Consumption can result in subsequent adjustments of planned receipts.

B.

Consumption can reduce the originally planned production quantity.

C.

Consumption takes place with the planning material.

D.

Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.

Full Access
Question # 29

What sequence do you follow in master data maintenance to define the production of a material?

A.

Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center

B.

Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing

C.

Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center

D.

Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing

Full Access
Question # 30

Where can you define the valid receivers for production order costs?

A.

In the costing variant

B.

In the settlement profile

C.

In the valuation variant

D.

In the production scheduling profile

Full Access
Question # 31

Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

A.

Standard values (routing)

B.

In-house production time (material master)

C.

Transport time (routing)

D.

Formulas (work center)

E.

Operation control key (routing)

Full Access