Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CDCS Exam Dumps - EXIN EPI Certified Data Centre Specialist

Go to page:
Question # 9

What is the main reason to install Earth Leakage protection?

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Full Access
Question # 10

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

A.

There is no advantage, as it cannot be used with OM4 optical fiber cables.

B.

There is no advantage, as it creates additional heat load in the data center.

C.

It speeds up installation and provides an easy upgrade to transmission speeds up to 40 Gbit/s -100 Gbit/s.

D.

It is a very flexible system as it can be used for both copper cables and optical fiber cables.

Full Access
Question # 11

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Full Access
Question # 12

When installing a raised floor, can we use a spirit level bar to level the floor?

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Full Access
Question # 13

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Full Access
Question # 14

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Full Access
Question # 15

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

Full Access
Question # 16

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Full Access
Go to page: