Question # 4

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

Full Access
Question # 5

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?

A.

It depends on the type of gas-based fire suppression which will be installed.

B.

Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

C.

No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.

D.

No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.

Full Access
Question # 6

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?

A.

No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.

B.

No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.

C.

Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.

D.

Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.

Full Access
Question # 7

You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.

What should you recommend?

A.

Nothing, the UPS will be able to take care of the right levels of THDi

B.

Install a passive harmonic filter on the UPS

C.

Install an active harmonic filter on the UPS

D.

Install an isolation transformer rated at K13 or K20

Full Access
Question # 8

When shielding material reaches its saturation point, what will be the impact?

A.

The shielding material will reach its optimal shielding performance state.

B.

The shielding material will no longer be able to attenuate (reduce) additional EMF.

C.

The shielding material will increase its permeability factor.

D.

The shielding material will reach its maximum electrically charged state.

Full Access
Question # 9

What is the main reason to install Earth Leakage protection?

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Full Access
Question # 10

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

A.

There is no advantage, as it cannot be used with OM4 optical fiber cables.

B.

There is no advantage, as it creates additional heat load in the data center.

C.

It speeds up installation and provides an easy upgrade to transmission speeds up to 40 Gbit/s -100 Gbit/s.

D.

It is a very flexible system as it can be used for both copper cables and optical fiber cables.

Full Access
Question # 11

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Full Access
Question # 12

When installing a raised floor, can we use a spirit level bar to level the floor?

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Full Access
Question # 13

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Full Access
Question # 14

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Full Access
Question # 15

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

Full Access
Question # 16

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Full Access
Question # 17

Is it allowed to make design changes during the implementation phase?

A.

No, after a design freeze no further changes are allowed.

B.

Any change is fine as long as it is within the scope of the project.

C.

Yes, but only when time to implement is not exceeded.

D.

Only when there is a strong business and/or technical justification.

Full Access
Question # 18

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings