Question # 4

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

Full Access
Question # 5

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?

A.

It depends on the type of gas-based fire suppression which will be installed.

B.

Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

C.

No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.

D.

No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.

Full Access
Question # 6

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?

A.

No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.

B.

No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.

C.

Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.

D.

Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.

Full Access
Question # 7

You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.

What should you recommend?

A.

Nothing, the UPS will be able to take care of the right levels of THDi

B.

Install a passive harmonic filter on the UPS

C.

Install an active harmonic filter on the UPS

D.

Install an isolation transformer rated at K13 or K20

Full Access
Question # 8

When shielding material reaches its saturation point, what will be the impact?

A.

The shielding material will reach its optimal shielding performance state.

B.

The shielding material will no longer be able to attenuate (reduce) additional EMF.

C.

The shielding material will increase its permeability factor.

D.

The shielding material will reach its maximum electrically charged state.