E_S4HCON2023 Exam Dumps - SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade

Question # 4

You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.

A.

The upgrade of the PRD must be finished before you start new development in the DEV.

B.

The transport domain of systems DEV and QAS must differ from the transport domain of system PRD.

C.

The transport between Unicode and non-Unicode systems is forbidden.

D.

The upgrade of the PRD must be finished before you import any transports from the upgraded DEV system into the PRD.

Full Access
Question # 5

You are planning to use DMO of SUM to perform an "inplace-migration" to SAP HANA. What do you need to consider? Note: there are 2 correct answers to this question.

A.

The source system is non-Unicode and the target database is a scale-out system.

B.

The target database size increases temporarily because of the Shadow Repository.

C.

SAP HANA Landscape Reorganization required a manual step to edit a file.

D.

Network capacity between exporting and importing R3load processes must be.

E.

Unicode conversion is part of DMO only in case of target version AS ABAP 7.40 or 7.31.

Full Access
Question # 6

You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".

Where can you change this during the migration via the Utilities option of the SUM UI?

There are 2 correct answers to this question

Response:

A.

In SUM Phaselist

B.

In Process Control Center

C.

In SUM Parameters

D.

In DMO Migration Preparation

Full Access
Question # 7

Which downtime optimization technique requires the minimized downtime service (MDS) from SAP?

A.

Downtime Optimized DMO (DoDMO)

B.

Near-Zero Downtime Maintenance (nZDM)

C.

Near-Zero Downtime Technology (NZDT)

D.

Downtime Optimized Data Conversion (DoC)

Full Access
Question # 8

Which Guides contain information about SUM phases starting with "EU_CLONE_"?

There are 2 correct answers to this question.

Response:

A.

The SAP S/HANA Conversion Guide

B.

The Application Guide

C.

The major SUM Guide

D.

The DMO Guide

Full Access
Question # 9

You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?

Please choose the correct answer.

Response:

A.

/ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)

B.

/ASU/SSM (ASU Simple Schedule Manager)

C.

/ASU/SHOW_NOTE (Show SAP Note via Web-Browser)

D.

/ASU/START (Start ASU Toolbox)

Full Access
Question # 10

You are using the maintenance planner to calculate the required software components for your SAP S4HANA conversion. What do you need to know regarding SUM?

A.

AA

B.

As soon as the next SP level of SUM is available, the current version of SUM passes into "patch on request mode" immediately.

Full Access
Question # 11

Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

A.

Shadow on target creation

B.

Downtime conversion

C.

Silent data migration (SDM)

D.

Downtime migration

Full Access
Question # 12

You want to execute a Unicode Conversion only. Which approach do you need to follow?

Please choose the correct answer.

Response:

A.

SWPM using the Backup / Restore procedure

B.

SUM with DMO

C.

SUM without DMO

D.

SWPM using the Load procedure

Full Access
Question # 13

What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.

A.

Standalone AS ABAP with SAP_BASIS 752 and above

B.

SAP ECC system from SAP ERP 6.0 EHP 8

C.

SAP Solution Manager 7.2

D.

SAP S/4HANA Server 1809 and above

Full Access
Question # 14

You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?

Please choose the correct answer.

Response:

A.

Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.

B.

Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU &UC) procedure.

C.

Perform the Unicode conversion before the upgrade to SAP ECC 6.08.

D.

Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.

Full Access
Question # 15

Which are valid options to check the progress of the database migration in a Microsoft Windows environment?

There is correct answers to this question.

Response:

A.

Check the "Charts Control Center" in the SUM UI

B.

Check logs for jobs starting with "RSUPG_SGEN" in the system

C.

Check the log files written under "SUM\abap\log"

D.

Check the dump size of the database export on disk

Full Access
Question # 16

You performed a custom code check for an SAP S/4HANA conversion. In which transactions can you review the results?

There are 2 correct answers to this question.

Response:

A.

SYCM (Simplification Database Content)

B.

SAT (Runtime Analysis)

C.

ATC (ABAP Test Cockpit)

D.

SE80 (Object Navigator)

Full Access
Question # 17

What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?

Please choose the correct answer.

Response:

A.

An upgrade of the software components is performed, without changing the database type.

B.

A change of the database type is performed, without changing the software components.

C.

An SAP S/4HANA conversion is performed, without adapting the customer data.

D.

A migration of the SAP system to a new hardware is performed, without performing an SAP S/4HANA conversion.

Full Access
Question # 18

In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?

There are 2 correct answers to this question.

Response:

A.

Upgrading to SAP ECC 6.08 without using DMO

B.

Using DMO when applying Support Packages to SAP ECC 6.07

C.

SAP S/4HANA conversion to SAP S/4HANA 1709

D.

Updating to SAP ECC 6.07 using DMO

Full Access
Question # 19

Regarding an SAP Upgrade, What does the major SAP Note for the version of SUM you are using usually contain?

A.

The link to different patch levels to SUM

B.

AA

C.

The corrections to the SUM Guide

D.

An overview about possible upgrade paths

Full Access
Question # 20

You want to use the downtime-optimized data conversion for your SAP S/4HANA conversion. What is the main difference from a standard SAP S/4HANA conversion?

Please choose the correct answer.

Response:

A.

An additional temporary database is used during uptime

B.

Dedicated application tables are migrated in uptime

C.

TABIMJJPG is executed in uptime

D.

The repository is migrated in uptime

Full Access
Question # 21

What do you need to consider when performing the SI checks for an SAP S/4HANA conversion? There are 2 correct answers to this question.

A.

Depending on the SAP S/4HANA version, there are different SI check frameworks.

B.

The SI checks are executed in the development system and the results are transported into the subsequent systems.

C.

You need an SAP system based on AS ABAP 7.50 or above for the SI check framework.

D.

You need to build up a SI check framework by applying SAP notes.

Full Access
Question # 22

Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?

There are 2 correct answers to this question.

Response:

A.

Create "modified* versions of the objects that you need to adjust

B.

Release the transport request containing the modification adjustment

C.

Assign the transport request as a modification adjustment transport

D.

Manually activate the adjusted dictionary objects

Full Access
Question # 23

You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.

The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.

Why are 40 Process Buckets executed in parallel?

Please choose the correct answer.

Response:

A.

There is a maximum of 40 parallel R31oad processes within this specific downtime phase.

B.

SUM is still running in uptime; the number of 40 defined R31oad processes is considered.

C.

The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.

D.

These are 40 pairs of R3load processes, so there are 80 R3load processes running.