First time powering on UPS5000-E, make sure that the UPS main input switch, bypass switch, output switch, maintenance bypass switch and battery switch are all OFF
Depending on different layouts, the batteries can be deployed inside or outside FusionModule2000
When installing the power line on the UPS5000-E, if there are different sources on the main-lines and bypass, you need to remove the copper bars connected to the bypass and main lines first, and then connect the main circuit and bypass input respectively.
Whether the water distribution unit is equipped or not is based on installation scenarios
On the Current Alarm page of NetEco, filter criteria can’t set to search for the required alarms.
Modular Data Center is on-demand deployment, which avoids over-investment.
The UPS5000 option temperature and humidity sensor does not support cascading
For NetCol5000-A installation, the required time of preserving positive pressure is ( ) hours.