Question # 9

Three UPS5000-E-400Ks from a 2+1 parallel system. Which of the following statements about the parallel system are true?

A.

The parallel system capacity displayed on the LCD is 1200 kVA.

B.

The networkingmode is set to one-to-multiple for one UPS, and set to one-to-one for the other two UPSs.

C.

If the load is 420 kW, each of two UPSs carries 210 kW load, and the other one is standby and does not carry load.

D.

If the load is 420 kW, each of the three UPSs carries 140kW load.

Full Access
Question # 10

In large-scale data centers such as financial securities centers and telecom hubs. UPSs with a capacity of 200 kVA or higher are usually used. For UPS5000-E-200k, 12 V battery packs are usually configured as backup power instead of battery racks.

A.

True

B.

False

Full Access
Question # 11

In the FusionModule800 grounding solution, each cabinet is connected to the ground bar of the data center.

A.

True

B.

False

Full Access
Question # 12

As the altitude increases, the air density decreases, and the heat exchange capability of the air in a unit volume decreases. In this case, NetCol8000-E220 works with derating.

A.

True

B.

False

Full Access
Question # 13

When the outdoor unit of a Huawei air-cooled air conditioner is installed horizontally, what is the minimum distance between the outdoor unit and the wall or obstacle?

A.

100 mm

B.

200 mm

C.

300 mm

D.

600 mm

Full Access
Question # 14

Which of the following methods can be used to open the access control for the FusionModule2000 smart module?

A.

Fingerprint

B.

Card reader

C.

Password

D.

Facial recognition

Full Access
Question # 15

After the Power Echo is installed, the default user name is admin. The password is changed upon the first login. If the password is forgotten, it can be retrieved and reset through project verification.

A.

True

B.

False

Full Access
Question # 16

In a project 32 NetCol8000-Cs need to be networked for teamwork. Each group consists of four air conditioners. How should the northbound RS485 grouping switches, namely, toggle switches 2 and 3 on the main control module, be set for the last air conditioner in each group?

A.

ON, ON

B.

ON, OFF

C.

OFF, ON

D.

OFF, OFF

Full Access