Question # 17

The number of battery strings for the UPS5000-E can be adjusted. To avoid replacing the whole battery string due to one faulty battery and solve the battery maintenance difficulty of traditional UPSs, how many batteries the UPS5000-E (50 kVA power module) can adjust?

A.

30-40

B.

32-40

C.

32-42

D.

30-44

Full Access
Question # 18

The battery voltage of the UPS2000-G is 240 V for the 6-10 kVA capacity models, and is 480 V for the 15 kVA and 20 kVA capacity models.

A.

TRUE

B.

FALSE

Full Access
Question # 19

The number of batteries can be adjusted in the process of UPS configuration.

A.

TRUE

B.

FALSE

Full Access
Question # 20

For the 6-kVA UPS2000-G, a 1+1 parallel system requires () DB15 parallel cables to ensure that each UPS is connected by at least two parallel cables and to enhance the parallel system reliability.

A.

0

B.

1

C.

2

D.

3

Full Access
Question # 21

The built-in SNMP and ModBus card of the UPS5000-A reduce management investment costs for clients.

A.

TRUE

B.

FALSE

Full Access
Question # 22

The UPS5000-A 30-120 kVA can be wall-mounted.

A.

TRUE

B.

FALSE

Full Access
Question # 23

For 80 kW IT loads, configuring an 80 kVA UPS can meet the basic requirements.

A.

TRUE

B.

FALSE

Full Access
Question # 24

The highest temperature in the local area is () when selects T3 air conditioning?

A.

30-35°C

B.

35-43°C

C.

43-55°C

D.

55-65°C

Full Access