New Year Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

MB-335 Exam Dumps - Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert

Go to page:
Question # 25

A company implements Dynamics 365 Supply Chain Management.

Due to increased demand and limited space in the work cell area tor product LOOM, you must subcontract overflow work to another company. You have the following requirements:

• Locate a warehouse at the subcontractor building.

• Support picking and shipping activity tracking.

• Associate costs of transporting materials between the locations in the cost of the finished product.

You need to modify the production flow.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE Each correct selection is worth one point.

A.

Create transfer activities and assign them to the subcontractor.

B.

Create a new production flow version.

C.

Modify the overflow work operation and associate it with the subcontractor.

D.

Create a resource and work cell resource group for the subcontractor.

E.

Modify the overflow work activity and assign it to the subcontractor.

Full Access
Question # 26

A manufacturer uses Dynamics 365 Supply Chain Management.

The engineering department constantly revises product designs to stay current with the latest technology. The customer service department places orders lot the products but frequently adds a prototype product version that is not yet operational.

The manufacturer requites a solution that notifies customer service if a prototype version is selected on a sales order.

You need to configure the solution.

What should you configure?

A.

engineering product category

B.

version number rule

C.

product lifecycle stales

D.

product release policy

Full Access
Question # 27

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.

The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient

You need to ensure that the system is set up to support the manufacturing process.

Solution: Set up the IngredientB formula line as a phantom BOM.

Does the solution meet the goal?

A.

Yes

B.

No

Full Access
Question # 28

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.

The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.

You need to resolve the issue.

What should you do?

A.

Increase positive days.

B.

Decrease positive flays.

C.

Decrease negative days to be less than the item lead time.

D.

Increase negative days to be greater than the item lead time.

Full Access
Question # 29

A manufacturer uses route operations and job scheduling. You use a unique calendar for a conveyor line.

The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.

You need to adjust the efficiency percentage for the conveyor line calendar.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Full Access
Question # 30

A company uses separate finished good item numbers for size variations of the same product.

The company wants to minimize the number of variously-sized items that are created.

You need to perform the setup to allow variants in size to the product master.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Full Access
Question # 31

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP 01 to represent the painting service.

You need to create a subcontracting activity for the painting service.

Solution:

• Create a vendor warehouse for the subcontracting vendor.

• Create a vendor resource and add it to a new work cell for outsource painting.

• Create a production flow transfer activity and specify the vendor warehouse as The target warehouse.

Does the solution meet the goal?

A.

Yes

B.

No

Full Access
Question # 32

You need to set up the state control for sales of motorcycles.

Which two actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

A.

Create an inclusive restricted product list for United States. Do not add the motorcycle part to the list.

B.

Create an inclusive restricted product list for United States and add the motorcycle part to the list.

C.

Create an exclusive restricted product list for California and add the motorcycle part to the list.

D.

Create an exclusive restricted product list for Missouri and add the motorcycle part to the list.

Full Access
Go to page: