Question # 25

You use the master planning module for Dynamics 365 Supply Chain Management.

Planned production orders have been created.

Several sales orders are canceled in response to concerns about recent online reviews of a product.

You need to enable the appropriate action message.

Which action message should you enable?

A.

Increase

B.

Postpone

C.

Decrease

D.

Derived actions.

E.

Advance

Full Access
Question # 26

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.

The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor ingredient A is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.

You need to ensure that the system is set up to support the manufacturing process.

Solution: Create a dimension-based product master with variants and use the trade agreements to specify the different pricing.

Does the solution meet the goal?

A.

Yes

B.

No

Full Access
Question # 27

You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes. Each route uses different resources.

Materials are staged for consumption in different locations based on the resources being utilized for production.

You need to set up the formula to consume the goods from the correct line-side location.

What should you do?

A.

Select resource consumption and the operation for each line.

B.

Select the plan group and consumption operation for each line.

C.

Specify a site in the formula header.

D.

Select a warehouse and consumption operation for each line.

Full Access
Question # 28

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.

An employee discovers an error after a time and attendance record is approved and transferred. The payroll transfer has not been run. However, the time has been posted against the production order.

You need to reverse the transferred registrations.

What happens to the production order time posting?

A.

Negative values are offset through manual posting.

B.

Transactions are offset and neutralized.

C.

The production order is ended.

D.

The Production Report as Finished journal is posted.

Full Access
Question # 29

A company makes lubricants and greases that are used in the automotive industry.

The items use the standard cost method. Electricity and heating of the manufacturing building are allocated into the cost of goods based on the size and wattage of the machine used.

You need to ensure that the system is set up to support the cost allocation.

How should you complete the costing sheet configuration? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 30

You need to set up the correct production solution for the assembly area. Which solution should you implement?

A.

Standard warehousing with Manufacturing execution

B.

Standard warehousing for all transactions

C.

Advanced warehousing for all transactions

D.

Advanced warehousing with Manufacturing execution

Full Access
Question # 31

You need to modify the production order defaults for the manufacturing execution production order Start process.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 32

A lean manufacturing company is implementing Dynamics 365 Supply Chain Management.

The manufacturer subcontracts a part of the production process.

Items must support the subcontracting process.

The subcontracted cost must be included in production

You need to configure the production process to meet the subcontracting requirements.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.