11.11 Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 105

A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?

A.

Express trust in the team's ability to fulfill the necessary deliverables.

B.

Assert judgment over the team.

C.

Use a plan-driven approach in order to demonstrate control over the project.

D.

Increase the amount of subject matter experts (SMEs) to get better results.

Full Access
Question # 106

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

Full Access
Question # 107

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Full Access
Question # 108

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

Full Access
Question # 109

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Full Access
Question # 110

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Full Access
Question # 111

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).

B.

Implement fast-tracking to compress the schedule and improve the SPI

C.

Perform conflict management using the project's resource management plan.

D.

Review the risk management plan to evaluate the probability and impact of these delays

Full Access
Question # 112

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Full Access
Go to page: