Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 113

A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?

A.

Estimate the backlog items to forecast quality.

B.

Ask the senior manager to approve the user acceptance testing (UAT) plan.

C.

Review the quality management plan with the senior manager.

D.

Inform the senior manager that there are approved quality standards.

Full Access
Question # 114

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.

What should the project manager do first?

A.

Increase the capacity of the team to finish the project on time.

B.

Update the risk register and present a contingency plan to meet the deadline.

C.

Ask the team to propose a minimum viable product (MVP) to meet the date.

D.

Suggest to the customer to reduce the backlog to meet the date.

Full Access
Question # 115

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Full Access
Question # 116

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

A.

Risk to delivery

B.

Technical complexity

C.

Business value

D.

Estimation accuracy

Full Access
Question # 117

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

A.

Review the cost and schedule baselines for execution.

B.

Define change management for the new technology.

C.

Analyze the cost and identify the project benefits.

D.

Identify the risks in implementing the new technology.

Full Access
Question # 118

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Match the following common terms with their explanations that evaluate the buffers or constraints.

Full Access
Question # 119

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

A.

Support the project sponsor so the decision is made top-down and the team follows the provided direction.

B.

Support a voting exercise so all team members can express their opinion and the reason behind their vote.

C.

Support the product owner so only items with high business value are included in the next sprint.

D.

Support the project team so technical debt and infrastructure dependencies are included in the next sprint.

Full Access
Question # 120

A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was

being verified, it was found that the compliance part was not implemented in the project.

What should the project manager do next?

A.

Get an exception approval from the legal team.

B.

Request the team to implement the compliance.

C.

Ask the stakeholder to descope the compliance.

D.

Obtain approval from management and release.

Full Access
Go to page: