Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 201

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Full Access
Question # 202

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Full Access
Question # 203

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reactiontime.

C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

Full Access
Question # 204

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Full Access
Question # 205

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A.

30/40

B.

40/70

C.

30/70

D.

40/30

Full Access
Question # 206

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Full Access
Question # 207

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

A.

Develop different approaches based on team members’ motivation and ability.

B.

Develop a standard approach to provide feedback to all team members.

C.

Provide intensive oversight to the team members who performed poorly.

D.

Create a new standard performance measure based on project requirements.

Full Access
Question # 208

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

A.

Request a budget extension to get local resources experienced in agile.

B.

Plan to have the agile resources temporarily relocate to the project manager's location.

C.

Engage the agile resources through video conferencing on a daily basis.

D.

Advise the sponsor that the project will be delayed as agile training will be required.

Full Access
Go to page: