Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 201

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Full Access
Question # 202

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

A.

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

B.

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.

C.

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.

D.

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.

Full Access
Question # 203

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Full Access
Question # 204

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

A.

Email, call, or meet with each stakeholder separately to obtain their input

B.

Conduct a meeting to build the project management plan with the stakeholders who are available

C.

Escalate to the project sponsor that not all stakeholders are available for a meeting

D.

Meet with the project management team to build the project management plan before consulting stakeholders

Full Access
Question # 205

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

A.

Contact the human resources (HR) department to find new resources to replace this critical resource.

B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.

C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.

D.

Discuss the resource management plan with the project team for effective utilization of critical resources.

Full Access
Question # 206

Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?

A.

Verify the total float of each activity of the consolidated project schedule.

B.

Verify the critical path of the consolidated project schedule.

C.

Verify successors and predecessors of each activity of the consolidated project schedule.

D.

Verify the free float of each activity of the consolidated project schedule.

Full Access
Question # 207

The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).

What should the project manager do?

A.

Inform the stakeholders that the project goals are in the business case and change requests must be submitted.

B.

Secure approval from the most influential stakeholders on the project goals and the needed functionality.

C.

Host requirements gathering meetings where all of the stakeholders can identify their project goals until agreement is reached.

D.

Develop a list of project goals, secure sponsor approval, and then socialize them with the direct and indirect stakeholders.

Full Access
Question # 208

A scrum master noticed that one of the team members is afraid to ask questions, does not like to collaborate with other team members, and avoids taking responsibility for their actions. What is the likely reason that would cause a team member to behave that way?

A.

Lack of technical skills

B.

Fear of conflict

C.

Lack of experience

D.

Company culture

Full Access
Go to page: