Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 225

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Full Access
Question # 226

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

Full Access
Question # 227

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Full Access
Question # 228

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Full Access
Question # 229

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Full Access
Question # 230

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

A.

Seek help from experts to support the team member in fixing the problem.

B.

Facilitate a session to reach an agreement with the team as a whole.

C.

Negotiate with the customer a delay in the project delivery.

D.

Accept the team's request to reassign the team member.

Full Access
Question # 231

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Full Access
Question # 232

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Full Access
Go to page: