Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 353

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Full Access
Question # 354

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Full Access
Question # 355

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?

A.

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.

B.

Review and update the success criteria to ensure that the channel is not decommissioned.

C.

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.

D.

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.

Full Access
Question # 356

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.

Who is responsible for analyzing the new requirement and making the final decision?

A.

Project manager

B.

Scrum master

C.

Project sponsor

D.

Product owner

Full Access
Question # 357

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

A.

Ask the agile team to review the updated sprint velocity with the customer.

B.

Ask the product owner to review the prioritized backlog with the customer.

C.

Ask the agile team to review and update the quality management plan with the

customer.

D.

Review the impediments log with the customer.

E.

Send a detailed project management plan to the customer.

Full Access
Question # 358

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Full Access
Question # 359

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Full Access
Question # 360

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Full Access
Go to page: