Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 353

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Full Access
Question # 354

In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.

Which conflict resolution approach did the project manager use?

A.

Compromise

B.

Collaborate

C.

Synergy

D.

Force

Full Access
Question # 355

An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)

A.

Communicate via email to the project's email distribution group.

B.

Communicate via instant messaging.

C.

Communicate via the project team's document management site.

D.

Communicate in the IT risk forum.

E.

Communicate verbally to the key project stakeholders.

Full Access
Question # 356

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Full Access
Question # 357

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Full Access
Question # 358

Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.

What should the project manager do to prevent this from happening again?

A.

Review the risk impact of quality nonconformance.

B.

Review the communications management plan.

C.

Revise the quality management plan.

D.

Revise the product acceptance specifications.

Full Access
Question # 359

A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team's workload effectively?

A.

Add additional temporary resources to the project to achieve the next milestone.

B.

Encourage open communication and involve the team in task distribution decisions.

C.

Assign additional tasks to high-performing team members to decrease the burden on others.

D.

Renegotiate the scope of the next milestone with the stakeholders to align with the team's capacity.

Full Access
Question # 360

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

Full Access
Go to page: