A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource's refusal?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.
What should the project manager do to avoid this situation in the future?
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?