Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 473

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

A.

Work with the product owner to assess the impact and reprioritize the product backlog.

B.

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.

Submit a formal change request and obtain approval from the change control board (CCB).

D.

Meet with the Scrum Master to determine if the development cycle can be reduced.

Full Access
Question # 474

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

A.

Request the vendor to provide the servers on time as penalties may be applied

B.

Wait until the project deadline is reached in order to use contingency funds

C.

Reach out to the vendor to determine a plan to get the project back on track

D.

Review lessons learned from previous projects and take action accordingly

Full Access
Question # 475

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan

Full Access
Question # 476

A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?

A.

Include the deliverable in the status report and resend it to the stakeholder

B.

Invite the stakeholder to the next iteration review

C.

Invite the stakeholder to the next daily meeting

D.

Schedule a meeting with the stakeholder to review the status report

Full Access
Question # 477

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

Full Access
Question # 478

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

A.

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.

Evaluate the most cost-effective containment action and use their influence to implement it.

D.

Assess what corrective action is appropriate and use their influence to implement it.

Full Access
Question # 479

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Full Access
Question # 480

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.