Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
What product defines the reporting requirements between the Project Manager and Team Manager?
Which product records any project outcomes perceived as negative by stakeholders?
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.