Question # 17

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Full Access
Question # 18

Which may be funded from a risk budget?

A.

Capturing identified threats and opportunities in the Risk Register

B.

Specific management responses to a project's threats and opportunities

C.

Producing risk summaries for inclusion in Highlight Reports

D.

Any remaining open risks after the project has been closed

Full Access
Question # 19

Which is an objective of the Managing a Stage Boundary process?

A.

Understand what has gone well and what can help the next stage

B.

Review and approve the next Stage Plan

C.

Assure the Project Board that all project products have been completed and approved

D.

Prepare an Exception Report to advise the Project Board of a forecast deviation from tolerance

Full Access
Question # 20

What product defines the reporting requirements between the Project Manager and Team Manager?

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Full Access
Question # 21

How many tasks does the product-based planning technique describe?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 22

Which product records any project outcomes perceived as negative by stakeholders?

A.

Business Case

B.

Project Plan

C.

Communication Management Strategy

D.

Project Product Description

Full Access
Question # 23

Identify the missing words in the following sentence.

At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

A.

Stage Plan

B.

Communication Management Strategy

C.

Follow-on action recommendations

D.

Quality Management Strategy

Full Access
Question # 24

Why would the Project Manager escalate an issue to the Project Board?

A.

The Project Board is responsible for determining the priority of all issues

B.

Direction is required on the best response for preventing the issue from occurring

C.

The issue is forecast to cause a deviation beyond stage tolerance and advice is required

D.

Escalating issues is a means of providing the Project Board with a regular update on their status

Full Access