Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

Prince2-Practitioner Exam Dumps - PRINCE2 Practitioner Exam

Go to page:
Question # 33

Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%.

Which 2 actions should the Team Manager take in response to this situation?

A.

Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.

B.

Update the Team Plan by increasing all future work estimates by 10%.

C.

Amend the Work Package and ensure that the revised targets are met.

D.

Escalate the situation in the next Checkpoint Report.

E.

Raise an issue that costs will exceed tolerance if the current trend continues.

Full Access
Question # 34

BUSINESS CASE

Here are three statements from the business case for the Health and Safety Project.

Under which heading in the business case (A-F) should they be recorded?

Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.

Full Access
Question # 35

Which statement is an appropriate entry for the Lessons Log?

A.

This is the first time that the Ministry of Food Hygiene (MFH) has been involved in outsourcing.

B.

Based on feedback from other government departments, the Ministry of Trade and Industry has provided the names of two outsourcing companies that are unreliable and should not be included as potential service providers.

C.

The feasibility study estimated that the outsourcing project would take two years to complete.

D.

Only the Information Technology Division and Facilities Division will be outsourced.

Full Access
Question # 36

While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log.

Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?

A.

MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.

B.

The Project Brief is a complex document and may not be approved by the Executive.

C.

There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.

Full Access
Question # 37

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?

A.

As deliverables of the project, all benefit reviews should be scheduled and documented in the Project Plan during initiation.

B.

Small projects do not require a schedule of benefit reviews as only one review is required towards the end of the project and this should be documented within the Business Case.

C.

Benefit reviews should be planned and recorded in the simple PID.

Full Access
Question # 38

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet been decided which of the photographers to use.

Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?

A.

She can represent the Marketing department.

B.

She previously had a successful career in publicity.

C.

The Marketing department will help to deliver the benefits of this project.

D.

The project will be funded from the business marketing budget.

E.

A number of the products will be produced by the Sales department and the Marketing department.

Full Access
Question # 39

Which of the following roles cannot be combined?

A.

Executive and Senior User

B.

Project Manager and Project Support

C.

Project Assurance and Team Manager

D.

Senior Suppler and Supplier Assurance

Full Access
Question # 40

Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

A.

Project Assurance

B.

Project Manager

C.

Corporate or Programme Management

D.

Project Support

Full Access
Go to page: